By Tim Davis, President and Managing Partner, Glick Davis & Associates
Most behavioral health groups that want to grow already know how to deliver care. What they don’t have is a development department: the people who pick the next market, get the license, find and build the site, hire the team, and get payer contracts signed before the first patient walks in.
That gap is where expansion plans stall. A group with three strong centers can spend two years trying to open a fourth, while a platform with the right development engine opens a site every few weeks.
I have built that engine from the inside and from the outside. Before consulting, I led strategy and development at Center for Discovery as it grew from about 10 residential sites to more than 60 in 14 states. I then led growth and development at Newport Academy, helping grow it from a regional Southern California brand into a national organization as its valuation rose from about $100 million to $1.3 billion in three years. Since then, our team at GDA has taken OCD Anxiety Centers from 4 regional treatment sites to 30 centers spanning eight states in two years.
De novo growth is also good business. At a 2024 industry panel, an investment banker who has advised 40 behavioral health companies said acquisitions are the fastest way to grow, but de novo delivers the best return. A behavioral health operator on the same panel said a well-run de novo PHP or IOP can reach break-even within a year (Behavioral Health Business).
This playbook walks through the five stages we use on every expansion, and the mistakes that sink most first attempts.
Stage 1: Choose markets on reimbursement and regulation, not just demographics
The most expensive mistake in de novo growth is opening in the wrong state. Population, income and competitor counts are easy to pull, so most groups stop there. The factors that decide whether a site succeeds are harder to see:
- Payer rates and contracting access. Reimbursement for residential, PHP and IOP varies widely by state and by payer. We track current rate ranges by service line, which states pay better, and where in-network contracts are hard to get.
- Payer concentration. In some markets, one insurer controls the commercial business. If that payer won’t contract at a workable rate, the demographics don’t matter.
- Licensing difficulty and timelines. Some states license a new IOP in weeks. Others take many months or require a certificate of need.
- Zoning and community climate. Residential programs face very different local politics from one county to the next.
- Workforce. Clinician supply and state HR rules shape how fast you can staff.
California and Texas show why “easy to open” isn’t the same as “easy to succeed.” Both have very little regulatory oversight for new outpatient programs, so getting open is fast. The problems come on the back end.
In California, the risk is employment law. Liability exposure for employers is high, and private equity firms are growing increasingly reluctant to invest there.
In Texas, the risk is payers. On paper the state looks ideal, with fast-growing metros and large commercial populations. But Texas has some of the worst behavioral health rates we see, and payers are often unwilling to negotiate. The market is also highly concentrated: an American Medical Association analysis found that Health Care Service Corporation, the parent of Blue Cross and Blue Shield of Texas, holds 60% of the state’s PPO market and a plurality or majority in all 26 Texas metro areas (Texas Medical Association). A program that can’t secure a workable contract with that one payer is fighting for what’s left.
We know California, Washington, Virginia, Texas, Connecticut and Utah especially well, and we can tell you where it is easier to do business and where the hidden roadblocks are.
Stage 2: Build the licensing strategy before you sign anything
Licensing is where most expansion timelines slip. Each state defines levels of care differently, sets its own staffing and physical plant rules, and moves at its own pace. A site that meets every requirement in California can fail inspection in Virginia.
We handle the full licensing process: researching state requirements, preparing applications, writing and editing policy and procedure manuals, managing change-of-ownership filings, and preparing for surveys. Just as important, we have working relationships with licensing agencies across the country, and especially close ties in Virginia and Washington.
Sometimes the rules themselves are the obstacle. In Virginia, we helped Odyssey Behavioral Health work with the Virginia Department of Behavioral Health and Developmental Services (DBHDS) to create a new license category for larger adult residential homes. The existing category capped homes at eight beds, which made the model hard to sustain. The new category allowed Odyssey to open two separate homes of more than 20 beds each.
We are often brought in when a group is already deadlocked with a state agency. Knowing who to call, what the reviewer actually needs, and how to reframe an application usually gets things moving again.
Stage 3: Find a site that can actually be licensed
A beautiful building is worthless if the zoning won’t allow treatment or the layout can’t meet the state’s physical plant rules. We screen every site against three questions before a client commits:
- Is the use allowed? Residential programs in particular can trigger conditional use permits, public hearings or neighborhood opposition. Outpatient PHP and IOP sites usually face fewer barriers, but medical-office versus general-office zoning still matters.
- Can it meet licensing and accreditation standards? Bedroom sizes, bathroom ratios, egress, accessibility, and space for group rooms and offices all vary by state and level of care.
- Does the deal make sense? Build-out versus renovation, lease versus purchase, tenant improvement allowances, and contingencies tied to zoning and licensing approval.
We negotiate leases and purchase agreements with those contingencies built in, so a client is never stuck paying rent on a building the state won’t approve.
We are often called in after a project has already stalled. In those rescues we have uncovered poor permitting, general contractors overcharging and underdelivering, landlords not holding up their end of tenant improvements or doing shoddy work, and construction that didn’t meet local permitting law. We have also seen groups complete a full buildout that conflicted with state licensing requirements, then pay for alterations to conform.
One client bought a 100-year-old converted church in which none of the past renovations had been permitted. We worked through the permitting and renovation and turned it into a licensed residential treatment home.
Stage 4: Run the build like a system, not a one-off
Opening one site is a project. Opening 30 is a production line. The difference is a repeatable process with clear owners, a standard timeline and someone watching every dependency.
Our project management team oversees each opening from start to ribbon cutting: permitting, contractor selection, construction or renovation, furniture and IT, fire marshal and health inspections, and the licensing survey. Every site runs on a Gantt chart that ties construction milestones to licensing, hiring and payer contracting, so no workstream waits on another by surprise.
How long does it take? From idea to ribbon cutting, a PHP or IOP site can take a year. That covers selecting a market based on research, searching for the right site, negotiating the lease and tenant improvement buildout, hiring, training, and getting licensed by the state. Many groups take longer.
We recommend planning for 9 to 12 months for a first opening in a new state, and less for each opening after that. In select locations we have opened sites in as little as five months.
Stage 5: Staff, contract and accredit in parallel
The last stretch before opening has three workstreams that should all start well before construction ends.
- Hiring. Our recruiting specialists build the clinical and administrative team for each site and know the employment law of each state, from licensure rules for clinicians to wage and scheduling requirements. Hire too late and you open understaffed. Hire too early and you carry payroll with no revenue.
- Payer contracting. Credentialing and in-network contracts take time. Starting them late is one of the most common reasons a new site opens with an empty census.
- Accreditation. We prepare sites for The Joint Commission or CARF, including gap analysis, policies and staff training, so accreditation follows quickly after opening.
When these three run alongside construction instead of after it, the site opens licensed, staffed and able to bill on day one.
Five mistakes that stall de novo expansion
- Relying on brokers and landlords for zoning and construction. Most groups know very little about zoning or construction, so they lean on brokers, landlords and others who often lead them astray and take forever.
- Assuming what worked in one state will work in the next. Every state has its own licensing process and requirements. What got you licensed in Utah won’t necessarily get you licensed in Virginia.
- Overestimating their own edge. Groups overestimate their unique offering and marketing ability, and underestimate how strong the competition already is in the market.
- Picking states on demographics alone, without checking payer rates, payer behavior and the back-end risks covered above.
- Thinking they can do it on their own. Opening 30 centers isn’t rocket science. But most leadership teams are distracted with a thousand other things, and time-sensitive growth work always slides. When you dedicate a resource, and one that knows the pitfalls, it goes much faster.
An outsourced development department
Most groups ready to grow can’t justify building a full in-house development team, and PE sponsors don’t want to wait a year for one to get up to speed. That is the role we fill. For many clients we act as their entire development department: market strategy, licensing, real estate, construction oversight, hiring and launch, under one team accountable for the opening date.
Each engagement is staffed with a team lead, project managers, licensing experts, and people trained in sourcing sites and managing construction. It is also more affordable than hiring that team in-house. Even when we are running 15 to 20 openings a year for a client, our monthly fees, including travel, rarely exceed the monthly cost of a full-time person.
We also help when de novo isn’t the right answer. Sometimes an acquisition gets a platform into a market faster, and our mergers and acquisitions team can source and evaluate targets alongside a de novo plan.
Planning your next five sites, or your next 50? Email Tim Davis directly at tim@glickdavis.com. We’ll talk through your markets, your timeline and where we see the risks. You can also learn more about our healthcare strategy and growth services.
About the author
Tim Davis is President and Managing Partner of Glick Davis & Associates, where he leads the firm’s healthcare growth practice. Before consulting, he was head of strategy and development at Center for Discovery, growing it from 10 to more than 60 centers in five years. He later led acquisitions for Nvision Eye Centers and ran growth and development at Newport Academy, growing its valuation from roughly $100 million to $1.3 billion in three years. He also owns Manna Treatment, an adolescent and adult IOP in Duluth, Georgia.